This page features several sets of recent photos.
New - Mobile Phone Wallpaper - for camera
phones.
May & June 2008
|
|
|
Battery box suspended from the crane
|
|
|
|
Battery box being positioned
|
|
|
|
Battery box in place
|
|
|
|
40118 before the roof sections were replaced
|
|
|
|
Control cubicle section being moved into position
|
|
|
|
|
Control cubicle section being moved into position
|
|
|
|
Boiler roof section being positioned
|
|
|
|
Boiler roof section being positioned
|
|
|
|
One of the water tanks under cover ready for re-building work to start
|
|
|
|
Corrosion inside the water tanks
|
|
|
|
|
Corrosion inside the water tanks
|
|
|
|
40118 cab detail in its new undercover storage facility
|
|
|
|
The little end press during construction
|
|
|
|
The little end press during welding
|
|
|
|
The battery box showing how tight working conditions are
|
|
|
|
|
The top brackets are re-welded
|
|
|
|
The bottom brackets are re-welded
|
|
|
February & March 2008
|
|
|
Whilst cleaning the underside, the name of the steelworks producing the main loco frames becomes apparent
|
|
|
|
Loco underside after the first coat of undercoat
|
|
|
|
New electrical conduit being fitted adjacent to the boiler
|
|
|
|
The inside of the new boiler hatch showing the hinge arrangement which reduces water ingress
|
|
|
|
Con rods during cleaning and checking
|
|
|
|
|
The boiler before any renovation work
|
|
|
|
The control cubicle after blue gloss applied
|
|
|
|
New load regulator wiring loom
|
|
|
|
Loco underside after its first gloss coat
|
|
|
November & December 2007 & January 2008
|
|
|
The complex conduit run from the resistor frame to the load regulator. The middle of the orange conduits was replaced in October
|
|
|
|
A fully re-wired resistor frame
|
|
|
|
Loco underside after de-greasing but before re-painting
|
|
|
|
New parts for the Air/Vacuum control valve
|
|
|
|
three removed piston con rods
|
|
|
|
|
A worn out 'little end'
|
|
|
|
A new little end bearing, compared witha worn bearing aside
|
|
|
|
View down a cylinder following piston removal
|
|
|
|
New wiring to the load regulator
|
|
|
|
Underside work continues
|
|
|
|
|
Water pipe showing the 'kinked' elbow before main pipe run was corrected
|
|
|
|
New main bearing nuts - made specially to order
|
|
|
|
A con rod during crack detection work
|
|
|
|
Loco underside in primer
|
|
|
|
Loco underside in primer
|
|
|
September & October 2007
|
|
|
Main steam supply pipe after re-fitting
|
|
|
|
Completed turbo-charger pressure gauge frame
|
|
|
|
Loco underside, after the air tanks have been removed before cleaning
|
|
|
|
Main 2 inch vaccum pipe being cleaned and re-painted
|
|
|
|
Second cab heater during spraying
|
|
|
|
|
General view of the second resistor frame after wiring had commenced
|
|
|
|
Close up of the resistors being wired, showing the numerous wiring clamps
|
|
|
|
Main crank shaft with two of the piston big ends removed
|
|
|
|
Piston Conrods during the preparation for bearing replacement
|
|
|
|
A sample of the wiring being replaced in the main load regulator resistors
|
|
|
|
|
Loco underside during continued cleaning operation
|
|
|
|
Cylinder head showing valves before removal
|
|
|
|
Front view of cylinder head, showing rusty exhause port valves
|
|
|
|
A carbon coated air valve
|
|
|
|
Valves and springs after cleaning before re-assembly
|
|
|
|
|
Main resistor bank showing near completed wiring
|
|
|
July & August 2007
|
|
|
The damaged wiring tree of the load regulator resistors
|
|
|
|
Suited & booted, during cleaning
|
|
|
|
A primed section of the loco underside
|
|
|
|
Loco underside during cleaning
|
|
|
|
More underside work - this is the water tank mounting
|
|
|
|
|
Section of underside waiting to be cleaned, showing the water tank connection port
|
|
|
|
Brake system AV2 valve - which syncronises Air and vacuum
|
|
|
|
A cab heater during rebuilding
|
|
|
|
Cab heater after re-spraying
|
|
|
|
Scrap Load Regulator wiring after removal from the engine
|
|
|
|
|
Water strainer after re-fitting
|
|
|
|
Water strainer during re-construction work
|
|
|
|
Cubicle doors during undercoating
|
|
|
|
One of the main steam pipes after re-lagging
|
|
|
|
Turbo charger pressure gauges during re-assembly
|
|
|
|
|
After re-fitting the air/vacuum control valve, and water supply pipe
|
|
|
|
Turbocharger pressure gauges and their new mounting frame
|
|
|
|
Loco bodyside window during final painting
|
|
|
|
The three removed air tanks
|
|
|
|
Loco underside after three tanks have been removed
|
|
|
May & June 2007
|
|
|
Exhauster Speed Switch during re-fitting - note the new wiring to control the contactor
|
|
|
|
Number 2 cab wiring juction box after overhaul
|
|
|
|
The cab showing the XSS contact being re-fitted and the conduit arrangement under the floor
|
|
|
|
Bodyside area adjacent to control cubicle
|
|
|
|
The cubicle bodyside area after re-painting
|
|
|
|
|
Control cubicle cable tray
|
|
|
|
Load Regulator contact tip after repair to the silver contact face
|
|
|
|
After re-silvering, the contact tips are machined to the correct profile
|
|
|
|
A finished tip
|
|
|
|
One of the Air-Vacumm control valves
|
|
|
|
|
A cab heater during initial strip down, with faulty element identified
|
|
|
|
Drivers seat during fabrication
|
|
|
|
Turbo charger pressure gauge schematic drawing
|
|
|
|
Turbo charger pressure gauge frame during fabrication
|
|
|
|
Water strainer lid after cleaning and painting
|
|
|
|
|
Vacuum control valve after re-fitting
|
|
|
|
Close up of resistor wiring for load regulator
|
|
|
|
A merged photo of the load regulator resistor bank after re-fitting, during wiring
|
|
|
|
Bodyside bulkhead light after fitting
|
|
|
|
Cab heater conductor straps after overhaul
|
|
|
|
|
New floor plate adjacent to the cubicle
|
|
|
|
Resistor variable tapping connection system
|
|
|
|
Two turbo pressure gauges during spray painting
|
|
|
|
Underside of 40118, showing the water tank area being cleaned
|
|
|
March & April 2007
|
|
|
Cylinder head removal hoist
|
|
|
|
Cylinder head A1 during removal
|
|
|
|
Piston A1 during removal
|
|
|
|
Piston A1 on the bench
|
|
|
|
Resister frame after re-fitting
|
|
|
|
|
Asbestos stripping notice after a bit of 'spit and polish'
|
|
|
|
Loco side in undercoat awaiting its blue coat
|
|
|
|
Piston crown in situ before removal from the locomotive, showing carbon and debris
|
|
|
|
A bearing extractor tool during manufacture
|
|
|
|
Cooker area after fire pipe fitting
|
|
|
|
|
Load regulator mounting board after varnishing
|
|
|
|
Load regulator gearbox after overhaul
|
|
|
|
Load regulator backing board having fixed contacts replaced
|
|
|
|
Load Regulator fixed contact ring after overhaul
|
|
|
|
40118 during cleaning operations
|
|
|
|
|
40118 after being cleaned
|
|
|
|
Boiler air inlet after blanking off
|
|
|
|
Re-fitted foot step adjacent to the main generator
|
|
|
|
Oil Priming pump after re-fitting, during touching up of paint
|
|
|
|
The boiler inspection hatch frame after painting
|
|
|
|
|
Control cubicle with all doors fitted
|
|
|
|
The completed resister bank
|
|
|
January & February 2007
|
|
|
One of the failed main bearings clearly showing the copper inner shell
|
|
|
|
2nd resistor frame after cleaning and painting
|
|
|
|
Detail of reverser K before fitting of air cylinder
|
|
|
|
Montage of the re-fitted reversers
|
|
|
|
Nearing completion - the reversers after the re-fitting of the air rams.
|
|
|
|
|
Reversers after re-connecting the air supply (note the coiled pipes)
|
|
|
|
Load regulator cover in primer
|
|
|
|
The floor area below the cooker - before de-greasing work has started.
|
|
|
|
Cooker floor area - after cleaning
|
|
|
|
Engine room bodyside after removal of the water filter - to allow for cleaning and painting
|
|
|
|
|
Bodyside after removal of air/vacuum brake equipment
|
|
|
|
Bodyside after priming
|
|
|
|
A1 cylinder hear during stripping work prior to removal
|
|
|
|
Battery box during external painting
|
|
|
|
Resistor frame after re-fitting of all the separate resisters
|
|
|
Mobile Phone Wallpapers
If you have a camera phone, why not download one of these wallpapers for your
phone. Right click the wallpaper of your choice, and save to your hard
drive. Then transfer to your phone.
Page Top
Please note that in order to keep up load speed a quick as possible, these
photos have been saved low definition pictures - if you want a higher resolution copy
for any reason - why not ask?