Home Previous

Latest Photos
Previous Latest Photos News Archive

 

Featured Areas

Home

 

 

 

 

 

click for the Google Earth view of 40118

 

click here for 40118 from the air with Live Search

 

This page features several sets of recent photos. 

 

New - Mobile Phone Wallpaper - for camera phones.

May & June 2008

Battery box suspended from the crane

Battery box being positioned

Battery box in place

40118 before the roof sections were replaced

Control cubicle section being moved into position

Control cubicle section being moved into position

Boiler roof section being positioned

Boiler roof section being positioned

One of the water tanks under cover ready for re-building work to start

Corrosion inside the water tanks

Corrosion inside the water tanks

40118 cab detail in its new undercover storage facility

The little end press during construction

The little end press during welding

The battery box showing how tight working conditions are

The top brackets are re-welded

The bottom brackets are re-welded

 

February & March 2008

Whilst cleaning the underside, the name of the steelworks producing the main loco frames becomes apparent

Loco underside after the first coat of undercoat

New electrical conduit being fitted adjacent to the boiler

The inside of the new boiler hatch showing the hinge arrangement which reduces water ingress

Con rods during cleaning and checking

The boiler before any renovation work

The control cubicle after blue gloss applied

New load regulator wiring loom

Loco underside after its first gloss coat

 

November & December 2007 & January 2008

The complex conduit run from the resistor frame to the load regulator. The middle of the orange conduits was replaced in October

A fully re-wired resistor frame

Loco underside after de-greasing but before re-painting

New parts for the Air/Vacuum control valve

three removed piston con rods

A worn out 'little end'

A new little end bearing, compared witha worn bearing aside

View down a cylinder following piston removal

New wiring to the load regulator

Underside work continues

Water pipe showing the 'kinked' elbow before main pipe run was corrected

New main bearing nuts - made specially to order

A con rod during crack detection work

Loco underside in primer

Loco underside in primer

 

September & October 2007

Main steam supply pipe after re-fitting

Completed turbo-charger pressure gauge frame

Loco underside, after the air tanks have been removed before cleaning

Main 2 inch vaccum pipe being cleaned and re-painted

Second cab heater during spraying

General view of the second resistor frame after wiring had commenced

Close up of the resistors being wired, showing the numerous wiring clamps

Main crank shaft with two of the piston big ends removed

Piston Conrods during the preparation for bearing replacement

A sample of the wiring being replaced in the main load regulator resistors

Loco underside during continued cleaning operation

Cylinder head showing valves before removal

Front view of cylinder head, showing rusty exhause port valves

A carbon coated air valve

Valves and springs after cleaning before re-assembly

Main resistor bank showing near completed wiring

 

July & August 2007

The damaged wiring tree of the load regulator resistors

Suited & booted, during cleaning

A primed section of the loco underside

Loco underside during cleaning

More underside work - this is the water tank mounting

Section of underside waiting to be cleaned, showing the water tank connection port

Brake system AV2 valve - which syncronises Air and vacuum

A cab heater during rebuilding

Cab heater after re-spraying

Scrap Load Regulator wiring after removal from the engine

Water strainer after re-fitting

Water strainer during re-construction work

Cubicle doors during undercoating

One of the main steam pipes after re-lagging

Turbo charger pressure gauges during re-assembly

After re-fitting the air/vacuum control valve, and water supply pipe

Turbocharger pressure gauges and their new mounting frame

Loco bodyside window during final painting

The three removed air tanks

Loco underside after three tanks have been removed

 

May & June 2007

Exhauster Speed Switch during re-fitting - note the new wiring to control the contactor

Number 2 cab wiring juction box after overhaul

The cab showing the XSS contact being re-fitted and the conduit arrangement under the floor

Bodyside area adjacent to control cubicle

The cubicle bodyside area after re-painting

Control cubicle cable tray

Load Regulator contact tip after repair to the silver contact face

After re-silvering, the contact tips are machined to the correct profile

A finished tip

One of the Air-Vacumm control valves

A cab heater during initial strip down, with faulty element identified

Drivers seat during fabrication

Turbo charger pressure gauge schematic drawing

Turbo charger pressure gauge frame during fabrication

Water strainer lid after cleaning and painting

Vacuum control valve after re-fitting

Close up of resistor wiring for load regulator

A merged photo of the load regulator resistor bank after re-fitting, during wiring

Bodyside bulkhead light after fitting

Cab heater conductor straps after overhaul

New floor plate adjacent to the cubicle

Resistor variable tapping connection system

Two turbo pressure gauges during spray painting

Underside of 40118, showing the water tank area being cleaned

 

 

March  & April 2007

Cylinder head removal hoist

Cylinder head A1 during removal

Piston A1 during removal

Piston A1 on the bench

Resister frame after re-fitting

Asbestos stripping notice after a bit of 'spit and polish'

Loco side in undercoat awaiting its blue coat

Piston crown in situ before removal from the locomotive, showing carbon and debris

A bearing extractor tool during manufacture

Cooker area after fire pipe fitting

Load regulator mounting board after varnishing

Load regulator gearbox after overhaul

Load regulator backing board having fixed contacts replaced

Load Regulator fixed contact ring after overhaul

40118 during cleaning operations

40118 after being cleaned

Boiler air inlet after blanking off

Re-fitted foot step adjacent to the main generator

Oil Priming pump after re-fitting, during touching up of paint

The boiler inspection hatch frame after painting

Control cubicle with all doors fitted

The completed resister bank

 

January & February 2007

One of the failed main bearings clearly showing the copper inner shell

2nd resistor frame after cleaning and painting

Detail of reverser K before fitting of air cylinder

Montage of the re-fitted reversers

Nearing completion - the reversers after the re-fitting of the air rams.

Reversers after re-connecting the air supply (note the coiled pipes)

Load regulator cover in primer

The floor area below the cooker - before de-greasing work has started.

Cooker floor area - after cleaning

Engine room bodyside after removal of the water filter - to allow for cleaning and painting

Bodyside after removal of air/vacuum brake equipment

Bodyside after priming

A1 cylinder hear during stripping work prior to removal

Battery box during external painting

Resistor frame after re-fitting of all the separate resisters

 

Mobile Phone Wallpapers

If you have a camera phone, why not download one of these wallpapers for your phone.  Right click the wallpaper of your choice, and save to your hard drive.  Then transfer to your phone.

                    

 

Page Top

Please note that in order to keep up load speed a quick as possible, these photos have been saved low definition pictures - if you want a higher resolution copy for any reason - why not ask?

Send mail to the secretary with questions or comments about this web site